Why calendar and resource planning is not enough to prepare a QMS

58
2026.08.20
Cost-R
Tenders

Introduction: why construction plans are often not executed

A persistent paradox has been observed in the construction industry for a long time: even well-developed calendar, network and resource plans regularly demonstrate low feasibility.

Usually, the reasons are found in the planning itself: insufficient detail, errors in calculating labor intensity, inaccuracies in rationing, or unaccounted for external factors. However, in practice, the problem lies deeper.

Calendar and network planning (KSP) should determine when, in what sequence, and with what duration construction and installation work (CMP) is performed.

Resource planning (PR) answers another question: what resources, to what extent and in what time frame are needed to complete these works.

But even together they do not provide an answer to the key question: are all the conditions really created so that the work can be started on time and performed efficiently?

The KSP sets the timing and sequence. Resource planning determines the need for materials, equipment, and personnel. Together, they create a planned model of the desired outcome. However, both tools do not cover and do not take into account all aspects of the organizational and technological preparation of the implementation of the QMS.

Larix.Build: how to get your construction control in order and start managing the process.
See how Larix.Build helps

For example, the plans usually do not check:

  • Whether the mobilization and mandatory safety briefings have been carried out;
  • Whether the team has received all the necessary materials;
  • Whether permits for the equipment to enter the site have been issued;
  • Whether the team is aware of the work quality requirements;
  • Whether all certificates of inspection of hidden work have been drawn up.

As a result, everything is formally ready — the deadlines and resources have been planned. But in practice, it is impossible to start the work. The team is idle, the equipment is not being used, and the deadlines are being shifted.

According to the Construction Industry Institute (CII), the productive time of a construction team (tool-time) averages only 37% of the time spent on the site. Russian practice at individual projects records values of 23–25%. The rest is organizational and technological losses.

Pic. 1. The indicator of an employee’s productive time.

The solution:

Is to implement the Constraint Management (CM) methodology as a systemic mechanism for proactive organizational and technological preparation of construction and installation works (CIW).

How does constraint management differ from calendar‑network and resource planning?

To eliminate conceptual confusion, it is necessary to clearly distinguish between three tools that do not replace but complement each other:

  • Calendar‑network planning (CNP)
  • Resource planning (RP)
  • Limit Management (LM)
Calendar‑network planning (CNP)

Is a method for modeling the temporal and logical relationships between tasks.

CNP operates only with temporal categories. It does not verify the availability of resources, documentation, tolerances, or the confirmed readiness of preceding stages. The CSP records deviations after the fact (“actual performance is later than planned”), but does not allow them to be prevented. Even the most detailed network schedule does not provide information about why the work did not start: due to the absence of a drawing, material, tolerance, or construction readiness. Resource planning (RP) mainly covers material and technical support, labor resources, machinery and equipment, and finances.

Resource planning (RP)

The need and records the use of the resource, but does not confirm that all conditions for using the resource have been met by the time work begins. Typical gaps:

  • The material has been delivered to the on‑site warehouse, but it has not passed the incoming inspection; certificates and passports are missing; it has not been handed over to the crew for installation.
  • Cranes have been scheduled, but the slinger is not certified, and no technical inspection has been carried out.
  • The personnel is listed in the calculations, the team has been assigned, but the IDs have not been verified, the work permits for hazardous work have not been issued, and safety briefings have not been conducted.
Resource planning (RP)

Is a methodology for proactively identifying, tracking, and eliminating obstacles that block the start or completion of construction work. It answers the question: “What exactly is preventing work from starting or being completed?”. Functions of limit management:

  • Identifying constraints 6–12 weeks before the planned start of work.
  • Assigning responsibility for removing each constraint, with a division by stakeholder (client, general contractor, subcontractor, designer).
  • Setting deadlines for removing constraints, counting down from the start date.
  • Monitoring and tracking the removal of constraints.
  • Creating conditions under which, by the time the construction work begins, all necessary constraints (documentation, materials, equipment, personnel, permits, construction readiness, etc.) have been removed.
Why is Limit Management (LM) necessary?

Constraint management does not replace either calendar‑network planning or resource planning. It complements them by adding the missing link – verification of the actual readiness to carry out the construction work.

Comparative characteristics of three tools

Table 1. Comparative characteristics of CSP, PR, and UO
Parameter Schedule network planning (SNP) Resource planning (RP) Limit Management (LM)
Control object Temporal parameters (dates, durations, relationships) The volume and range of resources (materials, equipment, personnel) Organizational and technological conditions (documentation, tolerances, readiness)
Principle Reactive – detects deviations from the plan Reactive – detects deviations from the plan Proactive – eliminates obstacles in advance
Questions “When?”, “In what sequence?” “What and how much is needed?”, “When to place it?” “What could hinder it?”, “Who will resolve it and when?”, “Are all the conditions met?”
Information status Planned (dates) Planned (requirement) Actual (confirmed readiness)
Result Schedule (model) Resource plan Restriction removal plan (RRP)
Key thesis:

KSP and PR create a plan. Constraint management ensures the feasibility of this plan. Any calendar and resource schedule without a concurrently operating constraint management system will be merely a set of assumptions, not a document that guarantees the timely production of construction and installation works.

What needs to be taken into account when preparing a Gantt chart?

The preparation of Gantt charts must be carried out in accordance with the requirements established by the organization. Such requirements are formulated in the standard or methodology for Gantt chart planning and project control. As a rule, the methodology is fixed the following provisions:

  1. The necessary initial data for creating a Gantt chart
  2. Stages of creating a Gantt chart
  3. Rules for creating a work breakdown structure (WBS)
  4. Rules for detailing work across all areas of project activity
  5. Planned and controlled work parameters
  6. Description of the project planning and control process
  7. Participants in the project planning and control process and the rules governing their interaction
  8. Rules for updating the project and calculating the progress of work
  9. Reporting forms
Get the data and insights on how Larix.Build to get your construction control in order and start managing the process.

Basic concepts of the constraint management methodology

A constraint is a specific and verifiable condition, without which it is impossible to legally, safely, and technologically correctly begin or complete construction and installation work.

Limitation attributes:

Measurability
A limitation always has a clear and verifiable criterion for fulfillment. For example, “the certificate of inspection of hidden work is signed” — yes or no.
Targeted

Determined by a countdown from the start date of the construction and installation works, taking into account regulatory and contractual deadlines, for example, working documentation — within 60 days, materials — within 30 days, equipment — within 10–20 days).

Planned removal date

Determined by a countdown from the start date of the construction and installation works, taking into account regulatory and contractual deadlines, for example, working documentation — within 60 days, materials — within 30 days, equipment — within 10–20 days).

Category and group

The limitation refers to the unified classification (11 groups), which allows for their systematic management.

  • Schedule network planning (SNP)
  • Resource planning (RP)
  • Limit Management (LM)

What does the finished CSG look like?

As a result of the development of the CSG, a clearly structured plan appears with the allocation of responsibilities and a clear, achievable result of each package of work. A detailed plan shows the need for resources, the disbursement of funds, as well as a monthly-daily schedule of work, indicating the main physical volumes.

Level 1:
Project roadmap with key milestones
Level 2:
Reflects the main stages and objects of the project.
Level 3:
Demonstrates the consolidated work of individual sections of the facility.
Level 4:
Contains detailed work with resource content, reflecting the construction technology.

Classification of restrictions (11 groups)

The entire set of potential constraints is divided into 11 groups, covering the full life cycle of preparing and carrying out construction and installation work.

Groups of restrictions for the start of CMP

Table 2. Groups of restrictions for the start of CMP
№ Group Typical examples of content
01 Working documentation A set of drawings for the scope of work has been approved, submitted for production, and there are no conflicts with related sections.
02 Organizational and technological documentation The work plan, technological maps, and projects for crane operations have been developed and approved; the personnel have been informed.
03 Materials and equipment The specification has been drawn up, the order has been completed, delivery to the on-site warehouse, entrance control has been completed, certificates and passports are available
04 Machines, mechanisms, tools, accessories The applications have been confirmed, the equipment is on site, the staff is certified, the scaffolding has been assembled and inspected, and the formwork has been received
05 Occupational safety and industrial safety The briefings have been conducted (recorded in the logs), PPE has been issued, work permits have been issued, and safety barriers and signs have been installed.
06 Quality requirements Operational control checklists have been issued, the control procedure has been defined, and access for construction control has been provided.
07 Staff readiness The number and qualifications of staff have been calculated, the team has been assigned (by order), certificates and permits have been checked, and passes have been issued.
08 Construction readiness Geodetic marking has been carried out (marks, axes), previous work has been completed and accepted according to the records of hidden work, passageways and lighting have been provided.

Groups of restrictions for the completion of CMP

Table 3. Groups of restrictions for the completion of CMP
№ Group Typical examples of content
09 Taxiway and taxiway changes Requests for changes have been issued, the author’s supervision has confirmed, and changes have been made to the documentation (author’s sheets)
10 Completion of works The physical volumes have been completed, the actual labor costs, machine hours, and material consumption have been recorded and transferred to the KSP service.
11 Executive documentation The general and special work journals, as well as the certificates of inspection of hidden works, as-built geodetic diagrams, test reports, passports, and certificates have been submitted to the archive.
A standard checklist containing:

Each type of construction and installation work (construction of monolithic reinforced concrete structures, installation of metal structures, mechanized soil excavation, etc.) is accompanied by a standard checklist containing a list of coded restrictions with normatively established timeframes for removal.

Constraint management

The constraint management process consists of sequential cycles with fixed planning and control horizons.

Pic. 3. Planning horizons for CMP limitations

Pic. 4. Planning horizons for CMP limitations

Pic. 5. Planning horizons for CMP limitations

Stage 1

It is carried out in the form of an extended working meeting. Participants:

It is carried out in the form of an extended working meeting. Participants:

  • Constraint Management Coordinator (CMC) from the technical customer’s side
  • Construction manager from the general contractor
  • Engineering and technical supervision engineers from the customer and the general contractor
  • Construction control engineers (customer), specialists in occupational health and safety and industrial safety from both sides
  • Chief mechanic, supply specialist
  • Representatives of subcontractors (if necessary)

How the work proceeds: the team sequentially goes through all the planned types of construction and installation work (stages, structural elements). For each of them, all 11 groups of restrictions are checked using a standard checklist.

Important

All identified obstacles are recorded, both on the part of the customer and on the part of the general contractor and subcontractors. Even a potential restriction cannot be overlooked.

Result

A meeting protocol with a complete list of restrictions, including their codes, groups, preliminary deadlines for removal, and responsible parties.

Stage 2

Development of the Restriction Removal Plan (RRP)

After the meeting, based on the protocol, the restriction management coordinator transfers all restrictions to a single register (the PLAN‑R digital environment). For each restriction, the following are determined

Responsible
Specific official and party: customer (C), general contractor (GC), subcontractor (Sub), designer (D).
Planned date of removal
Calculated by counting down from the start date of the construction and installation works, taking into account the standards, for example, design documentation — within 60 days, materials — within 30 days, equipment — within 10–20 days.

The plan for removing restrictions is approved by the project manager (from the customer) and the construction manager (from the general contractor). All responsible parties receive extracts from the PSO.

Stage 3

Weekly monitoring cycle and meeting to lift restrictions

Monitoring of PSO implementation is carried out weekly on a fixed day with the participation of all responsible parties.

Preparation

2–3 days before the meeting, responsible parties send reports to the coordinator regarding their restrictions: current status, reasons for deviations, corrective measures, and an updated forecast.

Meeting (duration: 1–1.5 hours)
  • The constraint management coordinator displays the current status of the constraints with a color‑coded indication.
  • For “yellow” constraints (the deadline is close) and “red” ones (the deadline has been missed), an analysis is carried out: causes, additional measures, adjustment of deadlines; if necessary, issues are escalated to the project manager’s level.

The plan for removing restrictions is approved by the project manager (from the customer) and the construction manager (from the general contractor). All responsible parties receive extracts from the PSO.

Result

An updated PSO and a protocol with a list of activities and escalations.

Stage 4

Control milestone (10–14 days before the planned start date of the CMP)

The coordinator, together with the engineering department engineers of the customer and the general contractor, checks:

  • All restrictions for this scope of work have been lifted (or there is an approved plan to lift them before the start date)
  • A complete set of documentation is available: drawings, work plans, process charts, work permits, certificates, etc.

If the check is passed, a permit is issued to include this amount of work in the monthly (weekly) plan and allow the team to enter the facility.

Important

It is strongly discouraged (in fact, prohibited) to start the CMP if there is at least one non—lifted start restriction.

Stage 5

Monitoring the completion of the QMS and removing completion restrictions

After completion of the volume work, the following actions are performed:

  • The actual volumes, labor costs, and machine hours are recorded and submitted to the KSP service for updating the schedule.
  • The as‑built documentation is prepared: as‑built certificates of inspection of hidden works, as‑built geodetic diagrams, test reports, passports, and certificates..
  • The restrictions of groups 09 (changes to the design and technical documentation), 10 (completion of work), and 11 (as‑built documentation) are checked.

After confirmation, the restrictions are transferred to the “removed” status, and the PSO for this volume of work is closed.

Monitoring the completion of the QMS

As a result of the development of the CSG, a clearly structured plan appears with the allocation of responsibilities and a clear, achievable result of each package of work. A detailed plan shows the need for resources, the disbursement of funds, as well as a monthly-daily schedule of work, indicating the main physical volumes.

Developing our own format is an important step for every domestic software developer. With our own format, we can flexibly manage the format’s structure, adapting it to meet our specific needs, and also offer Russian BIM engineers a full‑fledged replacement for the foreign counterpart — IFC.
Maxim Grishin
Director of Business Development

Basic roles and distribution of responsibilities

For the successful implementation of the UR, it is important to clearly define the roles and areas of responsibility. Below are the key roles and their main responsibilities in the constraint management processes.

Table 4. Roles and their responsibilities in constraint management
Role Side Main responsibilities in the MA processes
Coordinator for Constraint Management (CUO) Technical customer Organization of identification meetings, management of PSOs, status monitoring, moderation of weekly meetings, report on “red” restrictions to management
Project manager Technical customer Approval of the PSO, resolution of disputes, removal of restrictions on the part of the customer (documentation, permits, access to construction control)
Head of Construction General Contractor Ensuring the lifting of restrictions by the general contractor (materials, equipment, personnel, etc.), coordination of PSOs, escalation of problems
VET Engineer (customer/General contractor) Both sides Control of the readiness of working and organizational-technological documentation, verification of completeness, participation in meetings.
Construction control engineer Technical customer Confirmation of the completion of preceding work (records of hidden works), verification of quality constraints.
Occupational safety and health engineer (customer / general contractor). Both parties Confirmation of compliance with safety requirements (briefings, work permits, personal protective equipment, guards).
Chief mechanic. General contractor Ensuring the availability and proper functioning of machinery and equipment, confirming requests
Supply specialist General contractor Tracking material deliveries, conducting incoming inspection (together with the construction control department)
Work supervisor (foreman) General contractor / subcontractor Providing information about the actual readiness of the work area, conducting visual inspections, providing feedback on restrictions
The latest publications